Build Timeline

Pre-Construction Timeline


Day 1-    07/09/12 - Tender signed
Day 21-  27/09/12- Variation 1 signed
Day 41-  17/10/12- Client check plans
Day 57-  02/11/12- Variation 2 signed
Day 78-  23/11/12- Final plan signed
Day 81-  26/11/12- Amended plans resigned
Day 92-  07/12/12- External colours and garden plan provided
Day 98-  13/12/12- Lodgement to Bingara
Day 102- 17/12/12- Submission rejected by Bingara
Day 103- 18/12/12- Re submit colours to Rawson
Day 125- 09/01/13- Rawson re lodged with Bingara
Day 130- 14/01/13- Bingara approve plans
Day 132- 16/01/13- Mine subsidence submission
Day 141- 25/01/13- Receipt of mine subsidence
Day 147- 31/01/13- DA lodgement
Day 149- 02/02/13- Colour appointment
Day 159- 12/02/13- Variation 5 signed off
Day 167- 20/02/13- Construction contract received
Day 169- 22/02/13- DA back
Day 172- 25/02/13- Reviewed contract with solicitor
Day 177- 02/03/13- Tile appointment
Day 179- 04/03/13- Contracts sent back to Rawson
Day 180- 05/03/13- Variation on DA
Day 181- 06/03/13- Re submission to council
Day 190- 15/03/13- Final council approval- final plans from Rawson
Day 194- 19/03/13- Application for construction certificate and estimators
Day 202- 27/03/13- Construction certificate provided
Day 208- 02/04/13- Electrical appointment
Day 210- 04/04/13- Bank approval
Day 215- 09/04/13- ACC from bank received by Rawson

Building Timeline

Day 1-   22/04/13- File handed to SS
Day 2-   23/04/13- Received phone call from SS to introduce himself 
Day 9-   30/04/13- Land excavated
Day 12- 03/05/13- Piers
Day 15- 06/05/13- Plumbing completed and rio/styrofoam blocks delivered
Day 16- 07/05/13- Formwork completed
Day 17- 08/05/13- Slab poured and fences erected
Day 26 -17/05/13- Plumbing and drainage connections
Day 30  -21/05/13- Progress payment for slab
Day 33  -24/05/13- Termite Guard installed
Day 36-  27/05/13- Frames delivered and ground floor started
Day 38-  29/05/13- Windows delivered
Day 40-  31/05/13- First floor frames started
Day 44-  04/05/13- Bricks delivered
Day 45-  05/06/13- Frames complete and windows in
Day 51-  11/06/13- Bricking the house commences
Day 59-  19/06/13- Scaffolding goes up
Day 78-  08/07/13- Bricking complete
Day 80-  10/07/13- Top level of house brick cleaned
Day 86- 16/07/13- Gutters go up
Day 88- 18/07/13- Main roof complete
Day 95- 25/07/13- Eaves installed
Day 99- 29/07/13- Downpipes go up
Day 106- 05/08/13- Cedar cladding starts to go up
Day 107- 06/08/13- Painting to the top half of the house complete (eaves, pole, windows stained)
Day 109- 08/08/13- Cedar Cladding completed and dark wood replaced
Day 118- 17/08/13- Garage roof goes up
Day 123- 22/08/13- Electrical and a/c rough in
Day 124- 23/08/13- Carpenters install cavity sliders and exterior battens to facade
Day 128- 27/08/13- Ducted vacuuming roughed in
Day 129- 28/08/13- Wet areas waterproofed
Day 130- 29/08/13- Ground floor brick cleaned
Day 134- 02/09/13- Insulation goes in
Day 135- 03/09/13- Gyprocking begins
Day 141- 09/09/13- Stairs completed
Day 142- 10/09/13- Lock up!!
Day 145- 13/09/13- Kitchen installed
Day 149- 17/09/13- Tiling in bathrooms/laundry begins
Day 155- 23/09/13- Kitchen and bathroom benchtops and sinks are in
Day 157- 25/09/13- Painters begin internal painting
Day 166- 04/10/13- Internal painting completed
Day 170- 08/10/13- Electrical fit off and plumbing started
Day 173- 11/10/13- Garage door installed
Day 176- 14/10/13- A/C ducts installed, bathtubs, shower screens and mirrors in all bathrooms    
Day 177- 15/10/13- Verandah up, shelves in cupboards/wardrobes/pantry.
Day 178- 16/10/13- Main floor tiles started
Day 179- 17/10/13- Main floor tiles finished
Day 180- 18/10/13- Verandah up and house cleaned
Day 183- 21/10/13- Front of house brick cleaned
Day 186- 24/10/13- Flyscreens installed
Day 187- 25/10/13- Site fence removed
Day 192- 30/10/13- PCI
Day 194- 01/11/13- Driveway formed up
Day 198- 05/11/13- Driveway poured
Day 200- 07/11/13- Carpet started
Day 201- 08/11/13- Carpet completed and appliances installed
Day 202- 09/11/13- Painters come back to touch up/paint externally